Revaluating Budget Values

Use

You can revaluate the budget values of a project or chosen, selected WBS elements. In other words, you can increase or decrease the values by a certain percentage or amount.

Procedure

  1. Choose Accounting ® Project system ® Controlling ® Budgeting ® Original budget ® Change ® Original budget ® WBS element overview.
  2. In the WBS element overview, select the WBS elements that have the budgets to be revaluated.
  3. Choose Edit ® Revaluate.
    The Revaluate dialog box appears.
  4. Enter the percentage or amount by which you want to change the current budget. If you want to reduce the budget, enter " - " after the figure.
  5. When you choose Continue, the system changes the values accordingly.
  6. Save the budget values.